| No. |
Contract reference |
Date |
Customer |
End user |
Location |
Voltage |
Length of Line(km) |
Tonnage |
| 500KV |
275KV |
132KV |
33KV |
OPGW |
MT |
| 1 |
102/2009 |
2009 |
HGPT |
TNB |
132kV TL Double Circuit Papan to MengLembu |
132 |
|
|
6.8 |
|
7.5 |
183 |
| 2 |
266/2007 |
2007 |
Multi Discovery |
TNB |
Proposed 132kV Single Circuit TL Loop In/Out Into PMU Kg. Repah From Existing Kg. Gadek-Kelemak |
275 |
|
12 |
|
|
12 |
288.72 |
| 3 |
707/2007 |
2007 |
HGPT |
TNB |
132kV TL Bukit Beruntung-Ulu Yam-Proton City-Slim River to DC 282MVA |
132 |
|
|
61 |
|
61 |
1137 |
| 4 |
851/2006 |
2006 |
HGPT |
TNB |
132kV Double Circuit Transmission Line From Point X (AP26A) To PPU Tg. Gemok-Mainhead B |
132 |
|
|
30 |
|
30 |
648 |
| 5 |
833/2006 |
2006 |
HGPT |
TNB |
Proposed 132kV Double Circuit Transmission Line From Pmu Mersing 132/11kV To Point X (AP26A) Mainhead A |
132 |
|
|
30 |
|
30 |
648 |
| 6 |
25/2005 |
2005 |
TTSB |
TNB |
275kV High Capacity TL Kelemak To Melaka |
275 |
|
20 |
|
|
20 |
890 |
| 7 |
310/2005 |
2005 |
HGPT |
TNB |
275kV (1000MVA) TL From Paroi to Lenggeng |
275 |
|
27 |
|
|
27 |
1950 |
| 8 |
45/2005 |
2005 |
HGPT |
TNB |
275kV and 132kV TL Termination at PMU Rantau Negeri Sembilan |
275 |
|
3 |
1 |
|
4 |
2730 |
| 9 |
20/2005 |
2005 |
HGPT |
TNB |
275kV High Capacity TL Bukit Raja Shah Alam West |
275 |
|
7 |
|
|
14 |
500 |
| 10 |
606/2003 |
2003 |
Transpro |
TNB |
Design, Construction, Deviation and Dismantling Works for Implementation of 132kV & 275kV DC TL Semabok & Ujung Pasir |
132 |
|
1 |
|
|
1 |
30 |
| 11 |
Powertek 01:0001/2001 |
2001 |
HGPT |
Powertek Berhad |
275kC DC & 275kV132kV QC Powertek to Kelemak |
275/132 & 132 |
|
23 |
16 |
|
23 |
1490 |
| 12 |
2/2001 |
2001 |
HGPT |
TNB |
|
275 |
|
7 |
|
|
7 |
390 |
| 13 |
DN 2/2000 |
2000 |
Mahkota Technologies |
SESB, Sabah |
Sabah West Coast Grid Extension |
275/132, 275, 132 & 33 |
|
105 |
60 |
10 |
175 |
2380 |
| 14 |
277/2000 |
2000 |
HGPT |
TNB |
Rehabilitation Project for 132kV Transmission Line Package 2 Perak. |
132 |
|
|
30 |
|
30 |
1040 |
| 15 |
146/2000 |
2000 |
HGPT |
TNB |
Implementation of 132kV DC TL From Point X to Avetani Substation |
132 |
|
|
7 |
|
7 |
320 |
| 16 |
314/2000 |
2000 |
HAKIKAT |
TNB |
Upgrading 132kV Papan-Pengkalan-Gopeng Road Transmission Line |
132 |
|
|
11 |
|
|
620 |
| 17 |
T.3927 |
2000 |
HGPT |
SESB, Sabah |
Design, Manufacturer, Delivery, Installation, Testing and commisioning of 33kV Interconnecting Between Sandakan 132/33kV Main Intake S/S and Taman Tsun Nyen S/S Sandakan |
33 |
|
|
|
7 |
7 |
250 |
| 18 |
257/2003 |
2003 |
HAKIKAT |
TNB |
|
275 |
|
|
|
|
|
100 |
| 19 |
255/98 |
1998 |
HGPT |
TNB |
Implementation of 275kV & 132kV TL Projects for Transmission System Development 1997-Stage 2 |
132 |
|
|
55 |
|
55 |
1290 |
| 20 |
300/98 |
1998 |
HGPT |
TNB |
Implementation of 33kV Distribution Line Project for Pahang Darul Ehsan |
33 |
|
|
|
|
|
250 |
| 21 |
877/97 |
1997 |
HGPT |
TNB |
Supply and Erect 275kV & 132kV TL for TNB Transmission System Development - Mainhead A & C |
275/132, 275 & 132 |
|
100 |
72 |
|
172 |
5640 |
| 22 |
116/96 |
1996 |
HGPT |
TNB |
Distribution Network for 33kV Overhead Lines in Johor from Pasak to PPU Tenggaroh |
33 |
|
|
|
60 |
|
540 |
| TOTAL |
|
0 |
305 |
379.8 |
77 |
683 |
23314.720 |